Hi all,

 I started working with MPT and as expected progress is updated bottom-up from Feature level to Vision Prop.

But now I have a problem… It’s normal that progress is not being updated from Tasks and / or Bugs up to Deliverables, and then to Features and so on? Am I doing something wrong? Is some additional configuration required?

I found it strange since on "Introduction to the MPT" appears on the Additional Features section the following: "Automatic Rollups: Start/End Dates & Completed/Remaining work is automatically rolled up from the task to the deliverable to the feature work items". And that's exactly what's not happening on my environment

Thanks in advance for your help.

Best Regards,

Pedro

 

 

Jun 3, 2009 at 2:22 PM

Hi again,

We managed to solve the problem... basically the daemon service was not working properly with to different projects...

Since we only have a project it's working fine now.

Best Regards,

Pedro

Jul 14, 2009 at 11:13 PM

I'm also having the same issue but with the daemon service running on a single project.  Could something else be causing the roll-up updating to not occur?

Also, does this mean you need to run one daemon service per project?